Timeline 2018-10-03T14:27:36+00:00

WINDLIFE’s KOLA WIND PARK TIMELINE

Q3 2016

Bankable Wind Resource Study (2-year data) completed by GEO-NET.


Q3 2016

Grid connection study approved by the System Operator and the grid owner, FSK.


Q4 2016

50 years land lease agreement signed.


Q1 2017

Selection of wind turbine (depending on local content requirements).


Q2 2017

Participation in Russian Government Tender for subsidy (May-June 2017).


Q3 2017

Financial Closure.


2018

Start up of a dedicated production line by a designated OEM in the Russian Federation, in compliance with localisation requirement by law.


2021

Commercial Operation Date (COD).